Sera C.R. E. No. 24.
Kowloon Canton Railway.
BRITISH SECTION ESTIMATE.
Main Head Bridges
Sub. Head Major No.7.
Work One 60' Span T.Girder Chain 11:691
Drawing C.P.5. Mo.1291.
AMOUNT.
Quantity DESCRIPTION Rate Unit $ Cts. 060 0 Excavation in found. 10/- 60 00 Timbering and Puying. 500 00 17300 Concrete in found. 35/- cu. ft. 6055 00 4250 Masonry in Footings. 40/- 1700 00 23050 Superstructure. 40/- 9230 00 331 Coping and Bed Stones. 2/0 662 00 2000 Dry Stones behind Abuts. 10/- 201 00 1 60' Girder Span landed in Kowloon. 5500 00 1 60' Carriage to site and Erection. 500 00 Total 24717 00 Contingencies 10% 2471 70 Grand Total 27168 70