C.K.E. No. 24.

Kowloon Canton Railway.

Main Head

Sub. Head

BRITISH

Major No.6.

BRITISH SECTION ESTIMATE

Item DESCRIPTION Quantity Unit Rate AMOUNT Work One 60ft. girder at Chain 9:961, Drywing C.R.E. No.10371. $ Cts. 81 Excavation in founda. 30000 cub. ft. 10 300 00. Timbering and pumping. 500 00. Concrete in founds. 3800 cub. ft. 35% 1330 00. Masonry in Portions. 4100 cub. ft. 40/ 1640 00. Masonry in Superstructure. 23530 cub. ft. 40 $420 00. Coping and Redstones, Drystone at back of abuts. 240.ft. $30 7150 VI One 60 ft. Girder landed in Kowloon. One 3500 00. One 60 ft. Carriage to site erection and painting. 500 00. Total 20421 Contingencies 10% 2342 00. Grand Total $25764 60.