Kowloon Canton Railway.

C.R.E. No. 24.

Main Head: Formation

Sub. Head: Tunnels

BRITISH SECTION

Work: Buscon Hill Tunnel No.2.

DESCRIPTION Quantity Unit Rate AMOUNT Coolie Lines. 8 $1200/4 each $14,400 00 Stores. 10 $1000/ $10,000 00 Shops. 20 $500/ $10,000 00 Wash houses. 2 $2500/+ $20,000 00 WORKSHOPS &c. 2 $1500/ $3,000 00 8 $1200/- $9,600 00 3 $1800/ $3,000 00 ERECTION OF PLANT 2 Power Houses for main Drilling Lighting and Ventilating plant. $2500/ $5,000 00 Erection of above plant including carriage to site. $15000/+ $15,000 00 3 Hoists carriage to site & erection $8000/- $8,000 00 Erection of Ropeway. $30,000 00 WATER SUPPLY. South Side $2,000 00 North Side, $5,000 00 Total carried forward $7,000 00 $134,000 00 Contingencies 10% Grand Total
Share This Page