Form C.R.E. No. 24.
Kowloon Canton Railway.
BRITISH SECTION
ESTIMATE.
Main Head. Sub. Head Work.
III FORMATION.
TUNNELS.
SUMMARY.
DESCRIPTION Quantity Unit Rate AMOUNT Beacon Hill Tunnel.- Shafts Readings Widening Tining Quarters 50,424.00452,650.00
614,350.00
400,669.00
193,622.00 $
1,711,715.00
491,700.00 Tunnel No.2, 3 and 4. Total 2,305,415.00 Contingencies 10% Grand Total 2,820,3415.00