COP I.1

269

"Bon Accord"

Bill of Quantities for the erection of the proposed Clock Tower to the Blake Pier, Hongkong.

April, 1901.

Hongkong.

*

Excavation and Drains.

Excavate to foundations, part fill and ram, remainder carted away

369.00 cubes @ $3.00 = $1,107

Portland cement: concrete in foundations composed of one part cement, one part sand and five hard stone broken to pass 1" ring

238.00 @ $3.00 = $714

Granite rubble, bedded in cement

37.60 @ $3.00 = $112.80, 81.00 @ $3.00 = $243, Total = $355.80

Hard dry stone material, filled in under floors and well rammed

53.00 @ $1.60 = $84.80

Drains.

4" Glazed stoneware socketed drain pipe, jointed in cement and laid to fall

134 Feet @ $0.70 = $93.80

Extra to 4" Bends

9 @ $1.80 = $16.20

6" Intercepting Trap, with cleansing arm

1 @ $25.00 = $25.00

4" Gulleys and brickwork in cement; Inspection chambers, built of 9" brickwork in cement; and include tooled granite cover

2 @ $18.00 = $36.00, 1 @ $20.00 = $20.00

Bricklayer.

Brickwork in cement mortar

To Summary

219.00 cubes @ $30.00 = $6,570, Cement concrete filling above done

21.10 @ $14.00 = $295.40, 15.00 @ $27.50 = $412.50, Total = $707.90

316.50 @ $3.85 = $1,218.53

1-1/3" steel joists and centering

Extra to facing with glazed bricks

3/4" Cement rendering

Tile paving grouted in cement

Cement skirting 12" high

Balusters 12.9" high

21.6"

Granite sink on and including two half-brick walls in cement

Air bricks for Vent. Lav. 4 W.Ds.

10.85 @ $28.00 = $303.80

287 @ $1.378 = $395.33, 3 ft. @ $0.35 = $1.05, Total = $396.38

344.50 @ $1.02 = $351.39, 3 gs. @ $8.00 = $24.00, Total = $375.39

84 @ $8.60 = $722.40

238 @ $8.00 = $1,904, 9.60 @ $47.15 = $452.64, Total = $2,356.64

Sq. Ft.

30 @ $2.93 = $87.90, 140 @ $1.63 = $228.20, Total = $316.10

Lin. ft.

15 @ $0.24 = $3.60, 145 @ $0.48 = $69.60, Total = $73.20

No.

80 @ $0.38 = $30.40, 38 @ $1.00 = $38.00, 1 @ $9.00 = $9.00, 9 @ $12.00 = $108.00, 12 @ $50.00 = $600.00

Continued.

$8,885.35