locality.

9.

For the purpose then of accelerating the rate of progress I think it will be found advisable to order on a larger scale than I originally contemplated.

10.

The following is an approximate estimate of the Plant which I now recommend. See over.

RECR C.O. 17710 Estimate of Plant 30 SEP

Floating Crane $26,500

3 Block Barges @ $6,760 20,280

Steam Jug Steam Crane, Rails, diving gear, &c. already requisitioned from the Crown Agents 12,000

Sundry minor articles 2,000

4 Hopper Barges $9,500 each 38,000

If a second Floating Crane be required } 26,000

148,780

Contingencies 10 percent 14,878

Total = $163,658

Estimate

L.