2

boardock with a patent slip to hard up steam launches (vide tracing

B

2) I should submit to His Excellency the Administrator, the risk involved

in not proceeding with the boat dock reclamations on Government

on

account at the same time as those

of Messrs: Jardine and Matheson.

2. So long as the gap exists

there will be the danger of the

typhoon seas

undermining and annihilating

the new seawall and marine

embankment adjoining.

It is only when there is a continuous or unbroken

front of masonry presented to the

waves that safety is to be found, it would appear to be only

an act of

ordinary

C

3

58

ordinary precaution to set the boat dock wall in hand now, with

a view to getting it sufficiently advanced to form already

some sort

of protection by September, the month

most to be feared.

3. I have consulted Mr. Zeani as to Police requirements and beg to propose a boat dock or basin 200 feet

by 100 feet to form a safe

sheltered access to the patent slip, which is intended to haul the police

Steam launches out of danger in the approach of a typhoon.

4. The cost of the patent slip and basin will be $35,000 including

a swing bridge over the Kowloon

Praya