366

estimates, and specifications, and especially also the title deed and trust deed, and the latter document must

Cyp

fulfil the conditions required by paragraph 5 of Rule 129.

7. The application is erroneously based on the estimated value of the ground ($5000) and the estimated Cost of the building ($20,000) whereas the Scheme does admit of a grant for the cost of the ground and Confines the amount of the grant to a maximum of one half of the actual, not estimated, cost of the building and fitting up of the Schools here applied for, to be proved by certificate with balance sheet on completion of the building and convey. (paragraph 2 and 6 of Rule N:29

(Liquid) E. I Eitel

Inspector of Schools

20th January, 1882

£