OFFICE OF SURVEYOR GENERAL

(Art. of Instructions, No. 38)

ESTIMATE OF THE EXPENSE NECESSARY TO BE INCURRED FOR Preparing Site for

Chinese Hospital-

Supplementary-

REPORT AND ESTIMATE No. 27 OF 1889.

Dated 29 June 1889.


PLAN OR DESCRIPTION.

MATERIALS

PARTICULARS.

LABOUR.

TO BE ISSUED

TO BE PURCHASED

STORES.

MATERIALS

PORTION OF WORK TO BE PERFORMED BY CONTRACT.


The site granted for the New Chinese Hospital is situated immediately behind Possession Point, and will in fact be formed by cutting away a part of what was formerly called Possession Point Hill. The area granted measures 210 feet by 150 feet, a portion of which will have to be cut down to a depth of 50 or 60 feet, while the South and West sides must be sloped to an angle of about 30°. The earth removed will, as far as possible, be used for the Reclamation now going on West of the Harbor Master's Office, but the greater portion will have to be removed in boats to West Point or elsewhere.

The cost of cutting down the Hill, including blasting what stone may be met with, is estimated at $3000, provision for which expenditure will be provided in the Supplementary Estimates.


Earth cutting and removal 287 of Earth to Praya Removal of Earth not required for reclamation, to West Point 965 5709 Blasting Stone 2000 500 300 -- 200 Casualties.... TOTAL 3000

Approved,

(signed) R. G. MacDonnell

LH Moorsom

Surveyor General.