APPENDIX X
HIGHWAYS OFFICE
NEW HIGHWAYS PROJECTS COSTING OVER $100,000
COMPLETED IN THE FINANCIAL YEAR 1973-74
Project
(a) Roadworks, Drainage and Bridges
(i) Hong Kong
Approximate Cost $ Road and Drainage Works adjoining I.L.s 7863 and 7910 in Jardine's Lookout Area 273,000 Road and Drainage Works adjoining Chong Gene Hang College, Chai Wan 621,000 New Road from Deep Water Bay Road to Wong Chuk Hang Road 3,983,000 Tin Hau Temple Road Area Development, Road and Drainage, Stage II, Phase I 3,346,000 Construction of Roads and Drains fronting C.W.I.L. 33, 19 and 30, Chai Wan 708,000 Widening of Stubbs Road near Tourist Lookout Construction of Sewer in Deep Water Bay Road 132,000137,000 Wan Chai Reclamation - Roads & Drains, Stage II, Phase I Reconstruction of four sections of Roads in North Point District (Tong Shui Road, Electric Road, Power Street and North Point Road) 1,366,000
465,000 Access Road to Little Sai Wan 1,280,000 Construction of Bus Terminus at Wong Chuk Hang Low Cost Housing Estate 481,000 Class I Recreational Track in Tai Tam and Mount Parker Area, Stage I 119,000 Wongneichong Gap Road Widening and Formation of Cricket Ground 2,483,000 Construction of temporary reclamation access road, Chai Wan Reclamation 331,000 Surfacing work at Central Reclamation Stage V, Temporary Cargo Handling Area 114,000 Sewer extension and connection at 42P Chai Wan Sub-Division 103,000 Access Road and Ancillary Drainage Works from Nam Long Shan Road to Estate School and Block B, Wong Chuk Hang G.L.C.H. Estate 226,000 Road Works adjoining I.L. 8104 King's Road 210,000 Road Works adjoining S.I.L. 708 and 718 Shaukiwan Road Construction of Road and Drainage Works adjoining R.B.L. 854 & 856 Chung Hom Kok Road 202,000
214,000 A.I.L. 374 New Road along north side of Staunton Creek Nullah 182,000 Tin Hau Temple Road Development Drainage Works in Lily Street, Tai Hang 187,000
198,000