APPENDIX BB

WATERWORKS OFFICE

WORKS COMPLETED AND UNDER CONSTRUCTION AND PROJECTS UNDERTAKEN BY CONSULTANTS

(1) Works Completed

Project Approximate Cost $ Eastern Service Reservoir Roof Reconstruction 200,000 River Indus Flood Pumping Scheme 28,840 Sheung Shui-Tai Po Supply, Stage II 11,300,000 ... ... Wo Keng Shan Irrigation Reservoir, Investigations 33,000 North Lamma Reservoir, Investigations 30,000 Kat O Water Supply, Investigations 33,000 ... ... Lai Chi Kok Hospital Salt Water Supply Main 130,000 Waterworks Depots, Argyle Street and Bullock Lane improvements to working conditions... 305,000 ... ... Central District Salt Water Flushing System Stage I 1,300,000

(2) Works under Construction

Hong Kong Island Chai Wan Distribution System ... ... 1,000,000 Improved Supplies to Middle Gap, Black's Link, Shouson Hill and the Ridge ... Stanley and Repulse Bay Supply, Stage II 9,000,000 Pumping Main to Victoria Peak 4,250,000 ... 800,000 Central District Salt Water Flushing System, Stage I A 1,300,000 Jardine's Lookout and Tai Hang Areas, Improved Supplies, Stage I... Trunk Feed to Aberdeen Service Reservoir, Stage I and Conversion from Balance Tank to Service Reservoir 2,350,000 ... ... ... 770,000 Provision of a Standpipe Water Supply to High Level Villages at Shau Kei Wan 160,000 Wanchai Reclamation-Water Supply Stage I 750,000 Kowloon and New Kowloon Ho Man Tin Development, Stage II 6,500,000 Kowloon East Salt Water System 3,650,000 Kowloon West Salt Water Flushing System 3,250,000 Ham Tin Fresh Water High Level Supply 4,000,000 Kowloon Bay Reclamation Section A-Supply 670,000 Fresh and Salt Water Distribution Mains, Lung Cheung Road Development Area 1, South 320,000

199

Share This Page