APPENDIX P-Contd.
Project
Estimated Cost
$
Port Works
Light at Cross Connection Chamber near Chau Kung Island
15,000
Cover for Tai O Public Pier
88,000
Light Beacon at Gau Tau (Shek Ngau Chau)
90,000
Supply and Installation of Plant for cutting up poultry crates-
Kennedy Town
150,000
Light Beacons at Tai A Chau (Soko Islands) Yuen Kok (Lamma Island) and Fan Lau (Lantau Island)
112,000
...
...
...
...
Light Beacon at Pun Shan Shek (Bunsansiah Rock) ...
Navigation Light for Kai Fong Pier off 134 Milestone-Castle Peak Road
Provision of Mooring Bollards in the Rambler Channel Typhoon Shelter
Improvement to Breakwater at Three Fathoms Cove, Plover Cove Water Scheme Development Works
145,000
12,000
20,000
145,450
Resiting the Railway Terminus, Preliminary Works
2,200,000
Kowloon Bay Development Drainage Works-Stage I
5,260,000
Aircraft Long-Term Parking Areas, Kai Tak Airport
3,200,000
Extension of Aircraft Parking Aprons and Taxiways, Kai Tak Airport-Stage I
11,400,000
Kai Tak Airport Runway Extension
152,000,000
...
...
Services Hospital, King's Park, Ancillary Works
280,000
Drainage Works
Construction of Lai Chi Kok Submarine Outfall
1,874,000
...
Shing Mun River Flood Control Scheme, Stages I and II
Construction of Main Culvert in Kwai Chung West...
1,874,000
1,838,000
Remedial Works to Landslide Area in Ma Shan Village and associated road and drainage works
897,000
...
...
Purchase of screening plant and equipment for Yuen Long Sewage Disposal Stage I
1,400,000
Construction of Kwai Chung Intercepting sewer Extension
1,528,000
Removal and Disposal of Sewage Sludge and Screenings in Kowloon
894,000
179