The pump house, to supply water treated at Red Hill to the reservoir, was completed and installation of the pumps started.
North Point/Shau Kei Wan Supply, Stage II
10.31. To serve increased demand in Shau Kei Wan plans were prepared for a new 21" diameter water main, to provide additional supplies from North Point Service Reservoir.
Chung Hom Kok Salt Water Flushing and Fresh Water Supplies
10.32. A layout was prepared for the mains, to be laid as part of the road reconstruction.
Kwun Tong High Level Supply
10.33. In order to keep pace with the expansion of Kwun Tong development, work continued on a high level supply system necessitating new fresh and sea water storage reservoirs. Site formation for the two reservoirs was half completed, and indents were prepared for the necessary pumps.
Water supplies to Tsz Wan Shan and Wang Tau Hom Resettlement Estates
10.34. Work on construction of the fresh and salt water reservoirs, and the concrete frame for the pump house to supply these areas, together with electrical works and staff quarters, was completed. A contract was let for the construction of a 45,000 gallon mild steel fuel storage tank.
Yau Tong Supply
10.35. The fresh water main was extended from the Ham Tin Low Cost Housing Site to the Yau Tong Resettlement Estate. Site investigations and surveys for the Fresh and Salt Water Service Reservoirs required under Stages II and III were completed.
Kwun Tong New Town Water Supply
10.36. Fresh and Salt Water mains were laid in the Housing and Commercial zones and the Commercial Centre as required by development, and in conjunction with road reconstruction.
Choi Hung Estate Supply
10.37. Fresh and salt water mains were laid as required.
Valley Road Low Cost Housing Supply
10.38. Work was put in hand on provision of fresh and salt water mains.