and a third block of three floors with barrack accommodation for 40 single warders with garages at ground floor level.

Chi Ma Wan Prison Quarters

52. A pair of semi-detached two-storey houses for two prison officers and their families were finished, and revised sketch plans completed for 12 married quarters and 74 barrack quarters for prison warders in single-storey buildings. The latter have been so designed that prison labour can be utilized to fabricate precast concrete units to be used in the construction of the buildings.

Stanley Prison

53. The construction of additional prison workshops has started.

Cape Collinson Training Centre

54. Sketch plans for this training centre for young offenders have been approved and a start made on working drawings.

Tai Lam Chung Prison

55. On the completion of the Tai Lam Chung Dam project, the Contractor's works buildings were purchased by the Government for use as a prison for drug addicts. Conversion of these buildings together with additional works proceeded steadily throughout the year.

RESETTLEMENT BUILDINGS

56. On November 26th, H.E. the Officer Administering the Government formally opened Block 'L' at Wong Tai Sin, the one hundredth Resettlement domestic block to be completed.

57. The first multi-storey Resettlement block was completed in September 1954, and though several improvements of a minor nature have been incorporated in subsequent blocks, the basic design remains unchanged.

58. The most recent improvement has been the enclosure of the two courtyards of the H-block by a screen wall and staircase; this will not only provide some degree of privacy to the courtyard but increases the number of rooms on each floor by four, and provides scope for improved elevational treatment. Tenders recently received for estates to which this amendment has been incorporated show no increase in cost.