# Lo Fu Ngam (Stage II)

65. Site formation work started for a further four blocks containing some 800 domestic rooms.

# Tai Wan Hill (Stage II)

66. Work on the final block was completed in November. This contract had been delayed by site formation work.

# Wong Tai Sin (Areas A & B)

67. Phase I. The final seven blocks of this contract were completed by November. Work had been delayed by faults found in the piled foundations.

68. Phase II. The final four blocks of this contract were completed by October.

69. Phase III (a). Site formation, piling and construction work for a further six blocks commenced.

# Jordan Valley

70. Site formation and piling work for the section of the estate south of the nullah was completed, and tenders called for the construction of nine domestic blocks and one flatted factory block. Tenders have been called for site formation of the area north of the nullah which will provide sites for a further seven blocks.

# Kwun Tong

71. Site formation work for Stage I containing ten blocks was well in hand; piling of the first four blocks started but faulty work on piles delayed construction work. Site formation work started for Stage II for a further ten blocks.

# Chai Wan, Stage I

72. The site formation and piling for three blocks and a flatted factory were completed in December. One of the domestic blocks has been completed and construction work on the other two and the factory is in hand.

# Li Cheng Uk, Stage IV

73. Work commenced on the construction of two blocks, one of which required piled foundations.