2

CAP. 215]

Eastern Harbour Crossing

[1986 Ed.

Section

PART VI

Page

21.

THE CARRYING OUT OF THE CONSTRUCTION WORKS

Authorization under this Part sufficient authority to carry out works ...

16

22.

Road Company to submit a construction programme

17

23.

No works to commence without authority

17

24.

Road Company to submit designs

17

25.

Approval and exemption of designs by the Director

18

26.

Alteration of approved or exempted designs.

18

27.

Approval of methods of construction

18

28.

Approval of construction contracts

18

29.

Provisions supplementary to sections 22 to 29

19

30.

Other powers of the Director

21

31.

Diversion of cables, pipes etc.

21

32.

Other obligations of the Road Company...

22

33.

Precautions to be taken against the obstruction of shipping or aircraft

22

34.

Restoration of sea-bed and works area

22

35.

Minor or incidental works may be carried out without submission of design

22

PART VII

CONTINUING OBLIGATIONS AND PROVISIONS IN RESPECT OF

THE CONSTRUCTION WORKS: REGULATIONS

36.

Defects

**

37.

Repair of immersed tube and road works

38.

Provisions supplementary to sections 36 and 37

39.

Closure of immersed tube ...

40.

Utilities through the immersed tube ...

41.

Director may enter tunnel area and works area for certain purposes

42.

Information to be supplied by the Road Company and the Rail Company to

the Director

43.

Power to make regulations...

PART VIII

THE ROAD TUNNEL

44.

Road operating date

23

45.

Road Company to provide tunnel facilities

24

46.

Right to use of tunnel facilities ...

25

47.

Control and safety of tunnel traffic

25

48.

Application of other laws ...

26

49.

Operation of road tunnel area by Government

26

...

...

27

27

28

28

Share This Page