1985 Ed.] Building (Administration) Regulations

[CAP. 123

A 19

(2) Subject to regulation 11A, any one or more of such plans may be submitted for approval separately.

(3) Without prejudice to regulation 30(3), the submission of further particulars or other plans consequent upon the refusal of the Building Authority to give his approval under section 16(1)(i) or (2)(f) of the Ordinance shall be deemed to be a fresh application in respect of the plans which the Building Authority had refused to approve.

30. (1) The approval of the Building Authority in respect of the plans submitted to him shall be signified by----

(a) notice in writing in the prescribed form served on the

person making application therefor; and

(b) the stamping, signing and dating of one copy of such plans, other than structural calculations, which shall be returned to the authorized person or registered structural engineer.

(2) The Building Authority may, upon application therefor, give separate approval for any one or more of the plans submitted.

(3) For the purposes of section 15 of the Ordinance, the period after which the Building Authority shall be deemed to have given his approval of plans submitted to him shall be

(a) in relation to plans which are submitted for the first time to the Building Authority for approval, 60 days from the date on which the plans were submitted:

(b) in relation to plans which, having been previously submitted to the Building Authority for approval, are submitted to him again for approval so extensively revised as to constitute, in the opinion of the Building Authority, a major revision of such plans, 60 days from the date on which the plans were last submitted;

(c) in relation to any other plans which, having been previously submitted to the Building Authority for approval, are submitted to him again for approval, 30 days from the date on which the plans were last submitted.

(4) If the Building Authority is of the opinion that plans submitted to him again for approval constitute a major revision of any plans previously submitted to him for approval, he shall notify the appointed authorized person or registered structural engineer accordingly, not later than 30 days from the date on which the plans were last submitted.

(5)-(6) [Deleted, L.N.233/82]

31. Application for the consent of the Building Authority for the commencement of any building works or street works shown on any approved plans shall be made in the prescribed form.

32. (1) The consent of the Building Authority to the commencement of any building works or street works shall be signified by notice in writing in the prescribed form served on the person applying therefor.

[Subsidiary]

L.N.233/82

L.N.121/73.

L.N.153/73.

Approval of plans. L.S.188/74. Form 12.

L.N.11/73.

Application for consent to commence.

Form 13.

Consent to commencement.

Form 14.

1