26
CAP. 56
Boilers and Pressure Vessels
[1988 Ed.
(ii) where the size or design of the boiler is such that it is not possible for an appointed examiner to enter it in order to examine the internal parts thereof; and
(iii) without prejudice to the provisions of subparagraph (i) or (ii), whenever an appointed examiner considers it necessary;
(ca) where the boiler is uncertified and the Authority, by notice in writing to the owner, so requires, the boiler shall be subjected to an hydraulic test or to testing by a specified non-destructive technique; and (Added 87 of 1988 s. 16)
(d) finally, on the first occasion on which the boiler is again operated, the boiler, save for any economizer or superheater that may be fitted therein, shall be (Amended 87 of 1988 s. 16)
(i) examined when it is under the pressure that will be specified in the certificate of fitness as the maximum permissible working pressure at which it may be operated; and
(ii) subjected by the appointed examiner to a pressure accumulation test if he considers it necessary. (Replaced 67 of 1978 s. 16)
(2) The following provisions apply to the examination of a boiler for the purposes of section 24-
(a) where an appointed examiner considers it necessary, the boiler shall first be examined when it is cold and has been prepared for examination in the manner prescribed in section 37(1)(a), (c), (d) and (e);
(b) where an appointed examiner considers it necessary, the boiler shall next be subjected by an appointed examiner to an hydraulic test;
(ba) where the boiler is uncertified and the Authority, by notice in writing to the owner, so requires, the boiler shall be subjected to an hydraulic test or to testing by a specified non-destructive technique; and (Added 87 of 1988 s. 16)
(c) finally, on the first occasion on which the boiler is operated the boiler, save for any economizer or superheater that may be fitted therein, shall be- (Amended 87 of 1988 s. 16)
(i) examined when it is under the pressure that will be specified in the certificate of fitness as the maximum permissible working pressure at which it may be operated; and
(ii) subjected to a pressure accumulation test by the appointed examiner except where he considers that the superheater might be damaged thereby. (Replaced 67 of 1978 s. 16)
(3) The following provisions apply to the examination of a boiler for the purposes of section 25-
(a) the boiler shall first be examined when it is cold and has been prepared for examination in the manner prescribed in section 37(1)(a), (c), (d) and (e);
(b) where an appointed examiner considers it necessary, the boiler shall next be subjected by an appointed examiner to an hydraulic test; and