GENERAL INFORMATION REGARDING CONSTRUCTION.
Contractor.
Date commenced.
Date completed.
Amount
of Contract.
Cost of Materials, &c.
Total.
$
Access Road
Intake Dam and Temporary Conduit
1 32/1928
34/1923
Chung Sing.
17.7.23
31.4.26
118,468.19
$ 1.492.62 3.877.60
$3
128,838.41
27/1928
Ng Wah.
20.2.25
31.1.26
70,385.50
2,881.13
73,209.63
North Conduit
27/1923
Ng Wah.
20.2.25
31.1.26
71,768.57
259.50
72,028.07
Tunnels and South Conduit
29/1924
Sir Win. Armstrong Whitworth & Co.
25.11.24
12.26
1,052,344.35
21,299.78
1,073,644.13
Reception Reservoir
56/1924
Trollope & Colls.
3.12.24
12.26
156,094.01
8,179.87
164,273.88
Rapid Gravity Filtration Plant
44/1927
Yee Lee & Co.
29.6.27
12.28
52,601.38
158,788.80
206,390.27
Shek Lai Pui Service Reservoir
60/1928
H.K.E.P.D. & C. Co.
14.9.28
31.12.30
262,110.75
28,338.56
300,449.31
24′′ Trunk Main, Kowloon
Pipers Hill Service Reservoir
44/1924
Waterworks Annual Maintenance Contractors.
Ng Wah.
1925
1930
*147,314.27
319,390.20
465,704.53
6.9.24
Cross Harbour Pipe
64/1929
Netherlands Harbour Works.
8.10.29
31.10.25
23.2.30
129,012.45
7,087.52
136,699.97
39,436.00
190,536.29
229,972.29
24" Trunk Main and 18" Distribution Main, Hong Kong...
Waterworks Annual Maintenance Contractors.
1920
1932
Gardens Service Reservoir
{
40/1931 54/1932 f
15.9.31
Yee Lee & Co.
16.3.33
14.1.33
12.7.33
*22,489.57
184.534.11 16,795.00
t-
22,489.57
38,974.64
240,303.75
Byewash Reservoir
36/1929
H.K.E.P.D. & C. Co.
13.6.29
31.5.31
480,638.81
31,985.08
518,623.89
*Cost of laying.
Included in 24" Kowloon.