HONGKONG.

TYPHOON REFUGE.

STATEMENT TO 30тH Juxe, 1915,

(cide pages 10 and 11 of Hansard, 23rd February, 1911).

17

1915

No. 15

Laid before the Legislative Council by Command of His Excellency the Governor, September 9th, 1915.

Contract time for completion-5 years from the 27th October, 1910.

Contract price,...

Cost of Contractor's extras other than those for

which provision is made in the Contract,...

Total amount of Contract and Extras,

Divided into 60 months,

56 months at $33,633,

Amount earned by Contractor on work actually accomplished including sun retained under the provisions of the Contract in the hands of the Government,..

16th July, 1915.

$2,018,002

Nil.

$2,018,002

33,633 per month.

$1,883,448

$1,890,724

W. CHATHAM,

Director of Public Works,