Contract time for completion-5 years from the 27th October, 1910.

Contract price,

Cost of Contractor's extras other than those for which provision is made in the Contract,

$2,018,002

Nil.

Total amount of Contract and Extras, ...$2,018,002

Divided into 60 months,

44 months at $33,633,..

..$ 33,633 per month.

.$1,479,852

Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,

$1,503,514