45
HONGKONG.
TYPHOON REFUGE.
STATEMENT TO 30TH JUNE, 1914,
(vide pages 10 and 11 of Hansard, 23rd February, 1911).
No. 1914
12
Laid before the Legislative Council by Command of His Excellency the Governor, July 30th, 1914.
Contract time for completion-5 years from the 27th October, 1910.
Contract price,
Cost of Contractor's extras other than those for which provision is made in the Contract,
$2,018,002
Nil.
Total amount of Contract and Extras, ...$2,018,002
Divided into 60 months,
44 months at $33,633,..
..$ 33,633 per month.
.$1,479,852
Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,
$1,503,514
22nd July, 1914.
A. F. CHURCHILL,
Director of Public Works.