- 1.

HONGKONG.

TYPHOON REFUGE.

STATEMENT TO 31ST DECEMBER, 1912,

(vide pages 10 and 11 of Hansard, 23rd February, 1911).

No. 1913

1

Laid before the Legislative Council by Command of His Excellency the Governor, February 13th, 1913.

Contract time for completion-5 years from the 27th October, 1910.

Contract price,

Cost of Contractor's extras other than those for

which provision is made in the Contract,

Total amount of Contract and Extras,

$2,018,002

Nil.

Divided into 60 months,

26 months at $33,633,..

Amount earned by Contractor on work actually accomplished including sum retained under the provisions of the Contract in the hands of the Government,

9th January, 1913.

$2,018,002

.$ 33,633 per month.

.$ 874,458

.$ 770,503

W. CHATHAM,

Director of Public Works,