this contract has so far been carried on in a dilatory and unsatisfactory manner; the contract was accepted by the Government on the 17th January, but the contract was not signed until the 4thr March, one month and 18 days after the date of acceptance; and during the remaining portion of the year, only 7,616 cubic yards of rubble stone laid in foundations, backing of concrete blocks and sea wall, 28,995 cubic yards of earth and brick rubbish deposited in reclamations, 12,444 cubic feet of granite ashlar in sea wall and storm water drains, 640 cubic yards of cement and lime concrete, backing of sea wall and storm water drains, 550 lineal feet of stoneware pipe drains 15" in diameter and 257 lineal feet of stoneware pipe drains 12" and 9" in diameter have been laid. The whole representing less than one fourth of the work included in this contract.
148. Section No. 4.-Contract No. 25 was made with TSANG KENG on the 2nd April, 1895, for the construction of the rubble stone foundations of sea wall and embankment, the whole to be completed on or before the 31st January, 1896; 97,760 cubic yards of rubble stone have been deposited in place to the 31st December, leaving about 21,700 cubic yards still to be supplied; and the upper surface and foreshore levelled and trimmed,
149. Contract No. 34 was made with TSANG KENG on the 9th November, for the construction of 912 lineal feet of storm water drain in Po Yan Street, Hollywood Road and Queen's Road, to divert the large drain which discharges the storm waters into the Harbour, at the eastern end of the said Section. A large quantity of stone has been cut for this work, but the excavations of the trenches for the new drains have not yet been commenced.
150. Section No. 6.--Contract No. 32 made with KWONG CHEONG on the 5th September, 1895, for the construction of a temporary timber wharf on the western side of Pottinger Street was com- pleted in a satisfactory manner, and the wharf opened to traffic on the 12th November last.
151. A temporary embankment for the landing of cargo, &c., has been formed between Marine Lots 10A and 10B, containing 5,459 cubic yards of earth. C.S.O. 185.
152. Sections Nos. 6 and 7.-Eastern and Western portions.-Contract No. 20 was made with TSANG KENG on the 11th April, 1894, for the construction of the rubble stone foundations of sea wall (on a length of 968 feet), landing piers at the bottom of Pottinger Street and Pedder's Street, storm water drains and a portion of the embankment at the western end of the Reclamations; the work to be completed on the 31st January, 1895; during the year 1894, 95,068 cubic yards and in 1895, 36,984 cubic yards of rubble stone were deposited in place; the work is, however, still unfinished, some 1,200 or 1,300 cubic yards being required for its completion.
153. Contract No. 22 was made with YAU KUNG CHEUNG on the 11th December, 1894, for the construction of 2,169 lineal feet of storm water drains in D'Aguilar Street, Queen's Road, Pedder's Street, Old Praya, &c. The work under this contract was carried on with dispatch and the whole completed in a satisfactory and workmanlike manner on the 15th June, 1895.
154. Contract No. 27 was made with CHAN A-TONG on the 21st May, for levelling, trimming, concreting the upper surface of the rubble stone foundations of sea wall and forming bed for con- crete blocks on a length of 884 feet; constructing storm water drains and backing the first course of concrete blocks with rubble stone; comprising:--987 cubic yards of rubble stone, 315 cubic yards of concrete, 5,198 cubic feet of granite ashlar and 815 lineal feet of stoneware drain-pipes; the whole being completed in a fairly satisfactory manner on the 15th November.
155. Contract No. 28, made with TSANG KENG on the 5th June, 1895, for the erection of a temporary timber wharf opposite the lower end of Wardley Street, containing 3,340 cubic feet of timber, was completed in a satisfactory and workmanlike manner, and the wharf opened to traffic on the 14th October.
1059
156. Contract No. 21 of 1894, C.S.O. 1984, and extension, C.S.O. ; under this contract, 77,822 cubic yards of earth have been excavated, filled into the Hopper Barges and deposited by them in these reclamations below Ordnance Datumn, and 17,355 cubic yards of spoil from dredger have also been deposited in these reclamations below Ordnance Datum.
157. Government Piers.-The rubble stone foundations of Pottinger Street, Pedder's Street, and Murray Road Piers, containing 25,200 cubic yards of rubble stone, have been completed, except a portion of the foreshore and upper surface of the rubble stone between the Pedder's Street piers. The foundations of the piers at the bottom of Pottinger and Pedder's Streets are included in contract No. 20, and the pier at the bottom of Murray Road was constructed by CHAN A-TONG under contract. No. 30 dated 2nd July and completed on the 4th November, 1895.
The upper surface of the rubble stone foundations of the piers have been roughly levelled, the upper surface of the Pottinger Street pier reformed, trimmed, concreted and 219 cubic yards of Concrete Blocks set thereon.
158. Making and Setting Concrete Blocks.-Contract No. 24 made with Yau KUNG CHEUNG on the 24th February, 1895, for forming, levelling and constructing floor of Block Yard, containing 9,310 square feet of lime concrete 4" thick, 1,047 square yards of rendering upper surface in cement; and for the manufacture of 1,000 concrete blocks, containing 3,670 cubic yards of cement concrete and 15,641 cubic feet of granite ashlar external facing of the said Blocks; the whole being completed in a very satisfactory and workmanlike manner on the 23rd August, and on the 10th September this