408
CONTRACT No. 4.
RUBBLE FOUNDATIONS AND FILLING.
Section No. 3.-Total length 1,060 lineal feet commenced 22nd December, 1890, time of com- pletion 21st December, 1891. This work has been set out; 120,874 cubic yards of stone deposited in foundations leaving to complete Contract 49,226 cubic yards of stone and 58,176 cubic yards of earth filling.
CONTRACT No. 2.
RUBBLE FOUNDATIONS AND FILLING.
Section No. 7. Eastern Portion.—Total length 1,157 lineal feet commenced 10th April, 1890, time of completion 9th January, 1891. This work has been set out; 119,198 cubic yards of stone deposited 38,967 cubic yards of filling, leaving to complete Contract 5,800 cubic yards of stone 47,700 cubic yards of filling.
CONTRACT No. 5..
FOOTINGS, PLINTH AND FILLING.
Section No. 7. Eastern Portion.-Commenced 16th March, 1891, time of completion 30th September, 1891, 32,222 cubic feet of ashlar, 981 cubic yards of concrete and 1,071 cubic yards of rubble laid, leaving 1,020 cubic feet of ashlar, 150 cubic yards of concrete and 6,500 cubic yards of earth filling.
CONTRACT No. 6.
DRAIN, ICE HOUSE LANE.
Section No. 7. Eastern Portion.-Commenced 11th May, 1891, time of completion 10th November, 1891, 520 cubic yards of earth excavated 6,287 cubic feet of ashlar laid and 137 cubic yards of concrete laid, to complete 1,300 cubic yards of excavation 10,400 cubic feet of ashlar and 350 cubic -yards of concrete.
CONTRACT NO. 11.
DRAINS, WARDLEY STREET AND MURRAY ROAD.
Section No. 7. Eastern Portion.-Commenced 5th September, 1891, time of completion 4th February, 1892, Ashlar being dressed at Quarries.
CONTRACT No. 10.
PRAYA WALL AND FILLING.
Section No. 7. Eastern Portion.-Commenced 5th September, 1891, time of completion 4th December, 1892, Ashlar being dressed at Quarries.
Hongkong, 15th October, 1891.