PUBLIC WORKS SANCTIONED AND IN CONTEMPLATION.

Estimated Cost,

Expended Estimated to 31st Dec., Expenditure,

1889.

1890.

A 1. Central Market,

270,000

14,000

The estimate does not include the sum of $139,441 expended to 31st December, 1889, for purchase of land and erecting a temporary Market.

150,000

73,183

33,817

A 2. Gap Rock Lighthouse, .

The amount to be provided for Gap

Rock Lighthouse is estimated at $180,000 Deduct estimated value of Steam

Tender after completion of works 2/3rds of cost price $45,000,..........

30,000

Net Estimate,

.$150,000

+

A 3. Praya Reclamation (Ordinance No. 16 of 1889),

Government Contribution,

419,323

31,000

A 4. Praya Reclamation site for proposed Western

Market,

91,000

30,877

25,123

A

5. Training Albany Nullah and Branches,. B 6. New Road and Preparatory Work, Kennedy Road

Sites,

38,000

8,000

A 7. Bridge over Bowrington Canal,

15,000 7,000

2,000

4,000

B 8. Improvements Recreation Ground, Happy Valley,

The estimate does not include the diver- sion of the Canal and alteration of Race Course under consideration for which a further sum of $24,000 would be required,..

16,000

8,000

A 9. Gaol Extension under consideration, approximate

estimate,

140,000

B 10. Cattle Depôt Extension,

10,000

2,000

A 11. Slaughter-House and Sheep and Pig Depôts, B 12. Slaughter-House, Kowloon,

90,000

5,000

6,500

13. Public Laundries, approximate estimate,

25,000

B 14. Public Latrines,

17,000

7,000

B 15. Civil Hospital, Staff Quarters,

66,000

14,022

25,355

B 16.

Coolie Quarters,..

7,000

3,800

A 17.

Alteration and Additions (in con-

""

templation),

7,131

B 18. Lunatic Asylum for Chinese, A 19. Police Station, Aberdeen,

20,000

12,800

32,115

4,615

4,000

B 20.

"

"3

Quarry Bay, (Plans being pre-

pared),

7,000

A 21. Police Station, Kennedy Town, B 22. District School, Saiyingpun,

41,543

38,307

1,000

10,000

2,000

C 23.

Kowloon,

8,000

C 24. Additions to Government House,

40,000

25,000

B 25. Reconstruction of Governor's Peak Residence

(under consideration), ..

40,000

B 26. Quarters for Superintendent, Botanical and

Afforestation Department,

22,500

A 27. Magazine for Explosives and Pier, Stone Cutters'

Island,

17,625

4,000

5,000

C 28. Shaukiwan Market Extension,

3,000

C 29. Government Offices Extension and New Law

Courts (under consideration),

150,000

30. Rain-Storm Damages, (completed),

112,783

70,038

37,149

A 31. Epidemic Hospital Hulk, *.

50,000

58,600

TOTAL,.

1,929,520

231,042

318,644

* The construction of the Hospital Hulk is not under the charge of the Public Works Department. The

estimated Expenditure given in the return was obtained from the Colonial Secretary's Office.

NOTE.-New Water Mains expended from 1887 to 1889, inclusive,..

$184,292

Main Drainage and Sanitary Works expended from 1880 to 1889,

inclusive,

587,563

S. BROWN, Surveyor General.