THE HONGKONG GOVERNMENT GAZETTE, 13TH MAY,
1882.
RETURN OF PUPLIC WORKS FOR THE MONTH ENDED 30TH APRIL, 1882,—Continued.
Description of
Date of Original Order for Commence- ment of
Completion Commence-
of Estimate for
Present ment Condition
Amount
of Works.
of
of Estimate.
1881.
1881.
1881-82.
Expended
to
Balance
31st Mar., Remaining
1882.
$
c.
2,000
Nil.
Completed.
$
C.
2,000.00
:..
Works & BUILDINGS,—Continued. 11. – Maintenance of Praya Wall,
Incidental Services under $50,-
to underpinning and pointing ria Wall Lapsopwán.......... ROADS, STREETS & BRIDGES. 15.-Drainage and Sewerage,
Constructing New Drain through Inland Lots Nos. 48 and 71,... Constructing New Drain, &c., in
Burd Street,
Constructing New Drain in Sta-
tion Street between Po Yan Street and Pound Lane, Constructing Sewers in Taiping-
shin Street, Constructing New Sewer
in
Bonham Strand between Cle- verly and Morrison Streets, Taking up and reconstructing Sewer, &c., in Ladder Street, between Square and Bridges Streets,
Incidental Services under $50,-
to cleaning foreshore and mouth of drains in front of New East Street, Hillier Street, Cleverly Street, Queen's Street, and Praya East, covering Stones to drain above Pokfulam Road, constructing New connecting drain, and pipe holes, Queen's Rond Central,.. 15.--Bonds out of Victoria...........
Widening and reconstructing to a uniform width of 9 feet the upper portion of the Peak Road from Austin Arms to Mountain Luige,
17-
- Hvad & Street Contingencies.. Remaking Road, repairing Side Channels, Footpaths, &c., in Queen's Road, between Bon- ham Strand and Wardley
Street, Hemaking road, repairing Side
Channels, Footpaths, &c., in Queen's Road, between Eastern Market and Wardley Street,... Concreting Side Channel, reform- ing and repairing the Robinson Road between the Castle and Bonham Roads, Reforming and remaking Road, constructing Side Channels and concrete margins to the East
end of Battery Hill Road, and the North end of Pokfulam Rd., Incidental Sercices under $50,-
to Queen's Road East, Ship Street, Triangle Street, and Wantsai Roail, 19-Repairs to Bridges,
Leidental Service under $50,-
to painting No. 5 Bridge Shau- kiwán Road,
29. - Watering Streets,
In the City of Victoria,.
Widening Kennedy Road,
tion of Kennedy Road,
10,000
1,325.39
8,674.61
15th Jan., In progress.
27th Jan., Completed.
16th Feb., In progress.
16th Feb., In progress.
16th Feb., In progress.
14th Mar., In progress.
Completed.
8,000
1,250.78
6,745.99
23rd Mar., In progress.
14,000
1,794.42
9,205.58
24th Jan., Completed.
25th Feb., Completed."
10th Mar., In progress.
28th Mar., In progress.
Completed.
1.000
923.35
776.68
Completed.
Widening and reconstructing por-Į
Completed.j
4th Mar., In progress.
500
1,000
107.65
392.35
49.69
950.31
Harbour of Refuge at Causeway Bay,
Construction of Breakwater,
100,000
54,283.80
45,716.20
21st May, 7th June, 28th June, In progress.