13. PLANNING CONSULTATION

(OUTLINE/DETAILED)

14. RISK AND CONTINGENCY

Has a risk assessment been done?

If YES, is contingency based on it?

15. PROJECT BRIEF PREPARED

16. PES PROVISION AGREED

17. PRIOR INFORMATION NOTICE (WORKS) OR INDICATIVE NOTICE

(SERVICES) PUBLISHED IN THE OFFICIAL JOURNAL OF THE EUROPEAN COMMUNITIES (OJ)

17A. CONTRACT NOTICE(S) PUBLISHED IN THE OJ

If NO, explain

*DETAILS PUBLISHED IN THE OJ DATED 12 NOVEMBER 1993

18. CONTRACT STRATEGY

PREPLANNED TRADITIONAL

DESIGN AND BUILD

MANAGEMENT CONTRACT

CONSTRUCTION MANAGEMENT

19. CONSTRUCTION CONTRACT CONDITIONS

GC/WORKS

20. COST ESTIMATES

1. Resources

2. Works

3. Other (specify)

JCT

FURNITURE AND FURNISHINGS

4. Contingency

5. VAT (if not included above)

6. Total excluding inflation

7. Inflation

8. Total including inflation

YES

NO

Not decided

OTHER (Specify)

ICE

DEPT STANDARD FORM

Not decided

OTHER (Specify)

(A) - This submission

£ 3,050,000

23,124,000

900,000

(B) - Previous approval

dated 22/7/93

£ 2,850,000

22,358,000

1,000,000

My letter of 10 Aug

to Miss Elliman is releva

1,376,000

1,342,000

£28,450,000

£ 27,550,000

£28,450,000

£ 27,550,000

Page 75Page 76

21. BASIS OF COST ESTIMATES