To members of HK Steering Committee

Gremlin Duing Room.

166

HONG KONG: NEW CONSULATE-GENERAL AND BRITISH COUNCIL BUILDING: REVISED SCHEDULE OF REQUIREMENTS (SOR)

1. Since the last agreed SOR (dated Dec 1991) various substantial proposals, with space implications, have been made to revise/amend it as follows:-

Section

Function

Area

A1

Head of Post

32.5

9.5

1(a)

Head of JLG

32.5 + 32.5

2

PAS

23.0 + 6.0

Reason for change/comments

New area is standard for Grade 5 SP4/5

New requirement suggested by JLG and endorsed by HKD.

1 extra staff to cater for Al(a) suggested by JLG and endorsed by HKD.

4

Secretaries

23.0 + 4.5

"

11

14

Bag Keep

8.0

-

3.0

11

Rationalisation after discussion with Security Department

and Comms Sect. ISD.

18

)

)

OMIT/Delete

37.0

19

>

F15

SPACE previously allocated now required to cater for increased requirements for JLG which will only be

necessary for 3/4 years.

Technical Works 18.5+ 18.5 New requirement

suggested by OED as

large new building

will require

substantial TWO advice

or maintenance etc.

PCAS3.350