In respect of the provision of various ancillary services and facilities to

the airport users, the Shenzhen Airport Corporation has entered into joint venture

agreements with other organisations to provide airport hotel, airport catering and fuel

supply facilities. As a result, the total number of staff working directly for the

Shenzhen Airport Corporation was only around 600.

19.

The airport passenger terminal building is a three storey structure with a

total floor area of 42 000 sq. m. The first floor is for arrivals, linked up by

international and domestic streams of passengerways and equipped with auto luggage

rotary disk. The second floor is for departures (see photos at Appendix 7). The

terminal is designed to meet an annual handling capacity of 8 million passengers.

When the practical capacity reaches 5 million passengers, the airport authority would

plan and construct a second terminal dedicated to international flights. The current

terminal will then serve only as a domestic terminal.

20.

The airport cargo terminal is scheduled for completion by the end of 1992.

The cargo freight zone will occupy an area of 20 ha. Construction will be divided into

three phases. Each phase can operate independently. The area to be constructed in the

first phase will cover 1 ha. designed with a capacity to handle 80 000 tons of cargoes

per annum. When the whole cargo terminal is completed, the annual handling

capacity will reach 600 000 tons.