List of Contracts for New Airport and Related Projects
Brief Scope of Contract
18. Pui O 'B' Pumping Station - Civil
Contract
Prequalification (P) and Tender (T) Invitation Date
Commencement/ Completion Date
November 1993 (T)
April 1994
to
March 1996
Miscellaneous
1.
Lok On Pai Transhipment Centre Cargo Handling Facility (Contract No. 210)
22 June 1992 (T)
4 September 1992
2.
Lok On Pai Refurbishment Works - Construction (Contract No. 211)
to
April 1993 (Underway)
To be determined
Managing Department/ Officer-in-Charge
Water Supplies Department (Mr S K Fong - 829 4467)
Provisional Airport Authority (Mr David Corby - 824 7337)
Provisional Airport Authority (Mr David Corby - 824 7337)
Contractor/ Contract Sum $ M (MOD)
$ 29 M
as at 1st Ock,
Origin of Contractor
1992
Funding Source/
PWP No.
177WF
Gammon Construction
HK
PAA
Ltd.
2AG
$ 20 M
PAA
2AG
Note: (1) Contracts on the new airport and the railway are based on the latest information provided by the Provisional Airport Authority and Mass Transit Railway Corporation.
(2) Unless specified otherwise, contract sums are given in the Money of the Day prices. (3) All PWP Items except 1020CA are funded from CWRF.