List of Contracts for New Airport and Related Projects
Brief Scope of Contract
as at 1st Oc
1992
Prequalification (P) and Tender (T) Invitation Date
3.
West Kowloon Reclamation - Short term flow survey of existing drainage system (Contract No. UA 6/90)
25 September 1990 (T)
Commencement/ Completion Date
6 February 1991
to
10 July 1991 (Completed)
Managing Department/ Officer-in-Charge
Territory Development Department (Mr K Austin - 882 7190)
Contractor/ Contract Sum $ M (MOD)
Origin of Contractor
Funding Source/
PWP No.
Delta Surveys Ltd. $ 1.55 M
UK
354CL
4.
West Kowloon Reclamation - Inspection of sewerage system including CCTV and Topographical survey (Contract No. UA 4/90)
18 January 1991 (T)
6 March 1991
to
16 June 1991 (Completed)
Territory Development Department (Mr K Austin - 882 7190)
Dynarod Pearsall Ltd. $ 0.57 M
UK
354CL
5.
6.
7.
West Kowloon Reclamation - Construction of Yau Ma Tei Replacement Typhoon Shelter Phase II and Jordan Road Reclamation Phase I - construction
of about 4,000m of vertical
seawall/revetment, reclamation of about 75ha of land and reprovisioning of a PCWA. (Contract No. CV/90/09)
West Kowloon Reclamation - Northern
Area Phase I - reclamation of about 65ha
and construction of 1200m of seawall adjacent to Tai Kok Tsui/Sham Shui Po to provide land for the West Kowloon Expressway, the airport railway and other developments. (Contract No. UA 5/90)
-
West Kowloon Reclamation - Hinterland Drainage Package 1A reconstruction of about 1000m of existing stormwater culverts in the most urgent phase of a three-phase programme of essential improvements required to maintain adequate drainage capacity. (Contract No. UA 7/90)
28 December 1990 (T)
10 July 1991
to
July 1993 (Underway)
Civil Engineering Department (Mr Y C Lo - 762 5511)
Shui On-Boskalis J.V. $ 1,097.29 M
HK/
146CL Netherlands 365CL
11 January 1991 (T)
1 August 1991
to
1 May 1993 (Underway)
Territory Development Department (Mr K Austin - 882 7190)
Kumagai-Ham-Maeda J.V.
$ 1,553.9 M
Japan/ 366CL Netherlands/
Japan
13 September 1991 (T)
16 December 1991
to
7 October 1993
(Underway)
Territory Development Department (Mr K Austin -
882 7190)
Chui Hing Construction
HK
382CL
Co.,
Ltd.
$ 69.9 M