List of Consultancies for New Airport and Related Projects
Brief Scope of Consultancy
Report Date: 18 November 1992
Agreement No./ | Funding
Commencement Date/ Main Consultant
Managing Department/
Officer-in-Charge
Nationality (Origin) of Consultant
Agreement
Completion Date
Type/ Fee ($ M)
Source/
PWP No.
6.
Lantau Fixed Crossing - Secondment of System Engineer
June 1991 HPT System Ltd.
Highways Department (Mr K S Leung - 762 3600)
HK
May 1992 (completed)
CE 22/91
1
481TH 487TH
$ 2.04 M
7.
Detailed design,construction and completion of Route 3 Interchange and Advance Earthwork at north west Tsing Yi
8 August 1991 Scott Wilson - Parsons Brinckerhoff - Brian Clouston
J.V.
Highways Department (Mr J S V Chai - 802 1318)
HK(UK)/ HK(USA)/ HK(UK)
1995 (underway)
CE 23/91
DC
$ 36.47 M
487TH
492TH
476TH
8.
Lantau Fixed Crossing - Project Management Support Services
May 1992
Sir William Halcrow and
Partners Ltd.
Highways Department (Mr H S Kwong - 802 1333)
HK(UK)
June 1997 (underway)
CE 48/91 Specialist Staff
488TH
492TH
Services
476TH
$ 151.6 M
336TH
9.
Lantau Fixed Crossing - Construction stage Consultancy for Tsing Ma Bridge, KSM and Ma Wan Viaduct.
May 1992
Highways Department
HK(UK)
Mott MacDonald Hong Kong Ltd.
(Mr LH Williamson - 802 1324)
10. Lantau Fixed Crossing - Traffic Control
& Surveillance System
11. Lantau Fixed Crossing - Consultancy for
Contracts 4 (Lantau Approach Roads and Toll Plaza) and 5 (E & M Works)
July 1992
Highways Department
Mott MacDonald - Parsons Brinckerhoff -Scott Wilson
J.V.
(Mr H S Kwong - 802 1333)
HK(UK)/ HK(USA)/ HK(UK)
6 October 1992 Mott MacDonald Hong Kong Ltd.
Highways Department
HK(UK)
(Mr D S Paterson - 802 1340)
Page No. 4
June 1997 (underway)
CE 45/91
488TH
(PACKAGE I & | 487TH
II) C
476TH
April 1998 (underway)
$ 197.8 M
+ $ 20.47 M
(Provisional Sum)
CE 6/92
DC
$ 14.7 M (Lump Sum) + $1 M
(Provisional Sum)
487TH
mid 1998 (underway)
CE 20/92
488TH
D
$ 31.5 M