List of Contracts for New Airport and Related Projects
Brief Scope of Contract
Prequalification (P) and Tender (T) Invitation Date
Commencement/ Completion Date
Managing Department/ Officer-in-Charge
Report Date: 18 November 1992
Contractor/
Contract Sum
Origin of Contractor
$M (MOD)
Funding Source/
PWP No.
3.
Route 3 design stage 2, site investigation (Contract No. HY/91/17)
8 November 1991 (T)
23 December 1991
to
Highways Department (Mr C K Wong - 762 3622)
Lam Geotechnics Ltd.
HK
339TH
$ 15 M
4.
5.
6.
7.
23 July 1992 (completed)
January 1993
28 August 1992 (T)
to
Highways Department (Mr C K Wong - 762 3622)
$ 1,866 M (UBIP-1 Estimate)
505TH
January 1997 (tendered)
February 1993
25 September 1992 (T)
to
Highways Department (Mr C K Wong - 762 3622)
$ 2,700 M (UBIP-1 Estimate)
505TH
September 1996 (tendered)
April 1993
Highways Department
27 November 1992 (T)
to
(Mr C K Wong - 762 3622)
$ 852 M (UBIP-1 Estimate)
505TH
May 1996
Route 3 - Cheung Ching Tunnel and associated road works Construction of about 0.8km of dual 3-lane highway (generally at grade) on NW Tsing Yi, and a 1.6km long dual 3-lane bored tunnel within Tsing Yi. (Contract No. HY/92/02)
Route 3 - Kwai Chung Viaduct - Construction of 3km of dual 4-lane viaduct, generally 20m above ground level, along the Kai Chung Road Corridor (Contract No. HY/92/04)
Route 3 - Rambler Channel Bridge and associated roadworks - construction of a 0.5km dual 3-lane bridge crossing the Rambler Channel, and a 0.7km dual 3-lane viaduct along the south of Kwai Chung Park. (Contract No. HY/92/03)
Cheung Ching Tunnel E & M Works - Ventilation and Central Monitoring & Control System (Contract No. HY/92/25)
3 April 1992 (P)
29 May 1992 (P)
7 August 1992 (P)
February 1993 (P) August 1993 (T)
January 1994
to
December 1996
Highways Department (Mr C K Wong - 762 3622)
$ 121 M (UBIP-1 Estimate)
505TH
8.
Cheung Ching Tunnel E & M Works Tunnel Services (Contract No. HY/92/26)
| February 1993 (P) August 1993 (T)
January 1994
to
December 1996
Highways Department (Mr C K Wong - 762 3622)
$ 232 M (UBIP-1 Estimate)
505TH
West Kowloon 1.
Reclamation
West Kowloon reclamation
15 June 1990 (T)
31 August 1990
Construction of Yau Ma Tei
to
Civil Engineering Department (Mr Y C Lo - 762 5511)
Gammon Construction
HK
146CL
Ltd.
Replacement Typhoon Shelter Phase I (Contract No. CV/90/04)
28 September 1992 (completed)
$ 273.85 M
Page No. 5