List of Contracts for New Airports and Related Projects
Brief Scope of Contract
نه
Prequalification (P) and Tender (T) Invitation Date
Commencement/ Completion Date
Managing Department/
Officer-in-Charge
Central Reclamation - Phase I -
reclamation of about 20 ha and construction of around 1,110 metres seawall to provide land for the expansion of the Central Business Area and the Airport Railway Terminus. (construction entrusted to MTRC) (Contract No. UA 11/91)
8 June 1992 (T)
26 March 1992 (P)
December 1992
to
August 1996 (tendered)
Territory Development Department
(Mr K Austin - 882 7190)
Airport Railway
1. Interior Fit-Out for MDD Area 6th
Floor WTQ
April 1992
2. Airport Railway - Kwai Chung / Tsing
Yi Area Site Investigation (Contract No. 530A)
3. Airport Railway - Central Section Site Investigation (Contract No. 530B)
to
May 1992 (completed)
May 1992
to
December 1992 (completed)
Mass Transit Railway Corporation
(Mr R P Halstead - 751 3251)
4. Site Investigation for the AR alignment
on the West Kowloon Reclamation (plus extended works) (Contract No. C530D)
5.
Site Investigation for NE Lantau (Contract No. C530C)
September 1992 (T)
6. Rambler Channel Bridge (Contract No.
510)
Report Date: 17 December 1992
Contractor/
Contract Sum
$M (MOD)
Or of Comfor
Funding
Source/
PWP
No.
$ 1,491 M
343CL
[A]
MTRC
Mass Transit Railway Corporation
Bachy Soletanche Group
France
MTRC
(Mr R P Halstead - 751 3251)
June 1992
to
November 1992
(completed)
Mass Transit Railway Corporation
Bachy Soletanche Group
France
MTRC
(Mr R P Halstead - 751 3251)
August 1992
to
December 1992
Mass Transit Railway Corporation
Gammon Construction
HK
MTRC
Ltd.
(Mr R P Halstead - 751 3251)
Contract extended to include land site
investigation. (underway)
November 1992
to
February 1993 (underway)
July 1993
Mass Transit Railway Corporation
(Mr R P Halstead - 751 3251)
Mass Transit Railway Corporation
(Mr R P Halstead - 751 3251)
Page No. 9
Lam Geotechnics Ltd.
HK
MTRC
MTRC