CASH-FLOWS FOR THE AIRPORT
On 19 May, the Chinese side asked for information about the
Financial Support Package for the PAA.
Cash-flows
Cash-flows for the Airport Authority's operation up to the
year 2010 are attached.
1.
2.
The Airport is being constructed as a stand-alone project.
The attached plan represents a careful estimate of the airport's
future position, based on analysis of airport operations in Hong
Kong and overseas by independent financial consultants.
3. The plan is shown first under a mainstream case, which is the
case expected to occur, and then under a downside case,
4.
All figures are in money of the day. The inflation factors
used by the PAA in their calculations are the same as those used
by the Government.