Airport
NEW AIRPORT AND RELATED PROJECTS
LIST OF CONSULTANCIES TO COMMENCE IN THE NEXT TWELVE MONTHS
Brief Scope of Consultancy
―
1. Passenger Terminal Complex Detailed Design Consultancy - prepare detailed architectural and engineering design work required for the passenger terminal at the new airport
February 1992
Expected Commencement Date
Managing Department (Officer In-Charge)
Nationality Agreement
(Origin) Completion
of
Date
Agreement No./ Type/Fees($M)
Funding Source/
PWP No
Consultant
March 1992
Provisional Airport Authority (Mr Peter Wright - 802 3419)
12-93
PAA
IDC
Highways
1. Lantau Fixed Crossing - Construction stage Consultancy for LFC Contracts 1 and 2, (including design check for contract 2) and design/construction stages for Lantau
April 1992
Highways Department
5-98
(Mr K H Lee - 802 1333)
CE 45/91
C $156.5M
487TH, 488TH &
89TH
Approach Rd. & Toll Plaza
2. Lantau Fixed Crossing
April 1992
Traffic Control & Surveillance System
Highways Department |(Mr K H Lee - 802 1333)
4-98
[487TH
DC $15.8M
Management 1. Lantau Fixed Crossing - Provision of
support services to Project Management Office
March 1992
Highways Department (Mr K H Lee - 802 1333)
8-97
CE 48/91 Specialist Staff Services
476TH,
488TH &
1366TH
$180M
2. North Lantau Expressway - Provision of
Construction Management support services to Project Management Office.
To be determined
Highways Department
To be
(Mr K C Yeung - 721 6927)
determined
Specialist Staff Services
To be determined