to ensure proper interfacing, and to ensure that the ACP can be completed to the greatest
extent possible by June 30 1997. Balancing the complexity and interlinked nature of the
projects in the ACP against the progress made so far in the refinement of design and cost
estimation, we consider that $2.5 billion would be a prudent estimate for this overall ACP
contingency.
Comparison with July 1991 Estimates
6.
The updated ACP estimates compare with the July 1991 estimates as follows -
(All figures in $million at March 1991 prices)
July 1991
Transfer
Current
Net
Project
Estimates
between
Estimates
Increase/
Projects
Decrease
(1)
Chek Lap Kok Airport
43,600
0
46,300
2,700
North Lantau Expressway
4,300
500
5,790
990
Tung Chung Phase 1
2,600
-410
2,210
20
Lantau Fixed Crossing
12,100
-90
11,960
-50
Route 3
5,600
0
6,050
450
West Kowloon Reclamation
9,000
-380
10,010
1,390
West Kowloon Expressway
1,700
380
2,230
150
Western Harbour Crossing
3,900
0
4,150
250
Airport Railway
12,500
0
19,260
6,760
(2)
Central & Wanchai
1,800
0
1,900
100
Reclamation
Utilities and Others
1,500
0
2,360
860
TOTAL
98,600
0
112,220
+ 13,620
Notes: (1)
(2)
As design and contract documentation advances, it becomes apparent that certain parts of a project may be more efficiently carried by contractors under a different project. Figures in this column indicate the costs of such items transferred between projects.
The July estimate of $12.5 billion for the Airport Railway excluded works which form an integral part of other ACP projects and whose costs have been included in the respective project cost. For comparison, the current estimate of the Airport Railway of $22.16 billion is adjusted by $2.9 billion which has been included in individual cost of other ACP projects.
CONFIDENTIAL
機密