Airport Project Costs

3. The revised estimate for the cost of the airport

platform, the airport and its equipment is HKD 43.6 bn (at

March 1991 prices). This is an increase of 15% over the

1990 estimate of HKD 37.8 bn, although the cost of the

airport care project as a whole has gone up by only 1.6%

from HKD 97 bn to HKD 98.6 bn. Part of the reason for the

increase in the cost of the airport could be due to the

decision to increase the size of the platform from 1000 to

1275 hectares and to establish a runway separation of 1525

metres.

Airport Financing

4. The cost of the airport platform, airport and equipment will be financed as follows: HKD 13.8 will be in the form of

an equity contribution by Hong Kong Government, HKD 3.9 bn

will be cost of Government facilites including air traffic

control and control tower etc. Private investment in such

facilities as cargo and catering will amount to HKD 10 bn.

The remainder, HKD 15.9 bn will be debt.

5. In tendering for the platform contract the PAA would be looking for finance proposals for up to HKD 2 bn. The financial aspects are of major concern. Mr Allen will tell Ministers that the project is separate from HKG and will be independentally run. He has told Heap (BTC) that he wishes to concentrate on this aspect in his discussion with Ministers. There will no government guarantees from Hong Kong for the platform and lending will be against the project on a commercial risk basis. He will be meeting Malcolm Stevens (ECGD) to discuss financial support for the project.

BRIAFR/2