NEW AIRPORT AND RELATED PROJECTS LIST OF CONTRACTS COMPLETED

1 December 1991

Brief Scope of Contract

Tender Invitation

Date

Contract award/ Managing Department/ Contract Completion Dates

Site Investigation

1. Lantau Fixed Crossing Site Investigation

Phase 5

15 December 1989

March 1990

to November 1990

Officer In-charge

Highways Department (Mr KS Leung - 721 6540)

No.

HY/89/33 Gammon/Bachy

Contractor/ Contract Sum $m

Funding Source/ PWP No.

89TH

Soletanche Joint

Venture

$38.2M

2. Route 3 - site investigation for road aligment

(CRA 1 route) between Ting Kau and Sham Shui Po.

15 August 1990

to

24 September 1990 Highways Department (Mr

CK Wong - 721 6792)

HY/90/06 Bachy Soletanche

$15.5M

339TH

24 March 1991

3. Route 3 site investigation for tunnels

15 August 1990

5 September 1990

to

Highways Department (Mr|HY/90/07 Gammon CK Wong - 721 6792)

339TH

March 1991

Construction $14.5M

4. North Lantau Expressway Site Investigation

Phase 1

15 September 1990

November 1990

to

Highways Department (Mr CH Wan-721 6029)

HY/90/23 Geotechnics &

468TH

Concrete

May 1991

5. North Lantau Development Site Investigation

- Preliminary Report Stage

25 October 1990

December 1990

to March 1991

Territory Development

Department (Mr TD Armour 882 7250)

Engineering (HK) Ltd.

$18.5M

IS 11/90 Enpack (HK) Ltd. | 352CL

$7.73M

6. Chek Lap Kok Airport - Land site investigation -19 November 1990

airport site

7. Chek Lap Kok Airport – Marine site

investigation airport site

29 December 1990

to

Provisional Airport Authority PAA 04/90 Intrusion Prepakt PAA (Mr P Leung-802 3490)

6 May 1991

(Far East) Ltd

$12.6M

19 November 1990

29 December 1990

to

Provisional Airport Authority PAA 05/90 Bachy Soletanche (Mr P Leung 802 3490)

PAA

12 June 1991

$21.5M

8. Chek Lap Kok Airport – Marine site

investigation at Urmston Road & South Tsing Yi

22 December 1990

4 February 1991

to

Provisional Airport Authority PAA 06/90 Gammon (Mr P Leung-802 3490)

PAA

12 June 1991

Construction Ltd

$9.8M

9. West Kowloon Reclamation - Short term flow survey of existing drainage system

25 September 1990

to

10. West Kowloon Reclamation - Inspection

18 January 1991

of sewerage system including CCTV survey

22 February 1991

30 July 1991

8 March 1991

to

16 June 1991

Territory Development Department (Mr K Austin-848 2668)

Territory Development Department (Mr K Austin - 848 2668)

UA 6/90 Delta Surveys Ltd

$1.5M

354CL

UA 4/90 Pearsall Dynarod

Ltd.

354CL

$1.20M