NEW AIRPORT AND RELATED PROJECTS LIST OF CONTRACTS AWARDED (AT JANUARY 1991)
January 1991
Brief Scope of Contract
Contract Tender
Date
Contract awarded! Completion Dates
Managing Department/ Contract
Officer In-charge
No.
Contractor/ Contract Sum $M
Funding Source
(incl. PWP
No.)
Civil 1.
Engineering
West Kowloon reclamation Contract of Yau Ma Tei Replacement Typhoon Shelter. Phase I
15 June 1990
|24 August 1990
Civil Engineering Services
CV/90/04
to
|Department (Mr M S Leung
Gammon Construction
707/7146CL
15 June 1992
—
368 9768)
Ltd.
$234M
Site 1. Investigation
Lantau Fixed Crossing Site Investigation Phase 5
15 December 1989
March 1990
to
November 1990
Highways Department (Mr HY/89/33 K S Leung 721 6540)
Gammon/Bachy Soletanche Joint
89TH
Venture
$38.2M
2. Route 3 site investigation for tunnels
15 August 1990
5 September 1990
to
Highways Department (Mr HS Kwong - 733 2508)
|HY/90/07
March 1991
Gammon Construction $14.5M
339TH
3. Route 3 site investigation for road aligment
(CRA1 route) between Ting Kau and Sham Shui
Po.
15 August 1990
to
24 September 1990 Highways Department (Mr
HS Kwong - 733 2508)
HY/90/06 Bachy
339TH
24 March 1991
Soletanche $15.5M
4. West Kowloon Reclamation Site Investigation
7 September 1990
19 October 1990
to
18 October 1991
Territory Development Department (Mr K Austin - 848 2668)
UA 3/90
Lam Geotechnics L 707/7534CL $36.98M
5. North Lantau Expressway Site Investigation
Phase 1
15 September 1990
November 1990
to
Highways Department (Mr HY/90/23
K S Leung - 721 6540)
April 1991
Geotechnics & Concrete
468TH
Engineering
(HK) Ltd.
$18.5M