CAPITAL COSTS

ANNEX B

C

These comprise:

a.

Shipbuilder Contract Price

The total Contract Price for 5 No Vessels as established

at the date of placing the Contract (ie as stated at 1a, 1b, 2

and 3 of the Addendum to the Tender Form appropriate to the selected

option) (subject to adjustments). The following Additions/Abatements

to the Shipbuilder contract price will apply where appropriate:

(1) Price Variation Claims for variation of the Contract

Price due to inflationary factors ie increases in wages and/or

-

materials costs (Invitation to Tender (I) Clause 21 and

Schedule 16 refer).

<

(2) Launching Ceremony Any reasonable costs (within £8000

per vessel at October 1980 price level) in respect of launch

ceremonies (ITT Clause 35 refers).

(3) Technical Changes

Extras or rebates due to the introduction

of alterations to the requirement.

(4) Ship's Staff on Stand-by

-

(ITT Clauses 42 and 43 refer).

Possible extra or rebate due to

variation in the numbers or periods of ship's staff standing by

vessels under construction.

(ITT Clause 36.3 refers).

(5) Attendance of Ministry of Defence Supplied Items (MSIs)

Manufacturers Representative

J

Any admissible claims in respect of

the attendance, during construction of the vessels, or representatives

of the makers of MSIS.

(ITT Clause 32 refers) see item c. below.

(6) Delay and Dislocation

S

Any admissible claims in respect of

delay and dislocation to the construction of the vessels cutwith the