Original Requirements

$'m

Additional Requirements

Total Cost

$ 'm

Conversion of derelict

2.675

2.00

4.675

buildings for use as a

Police command post

>

>

Levelling of ground,

provision of shower,

toilet blocks and

}

water tanks (storage

>

capacity 45,000 litre

Additional water tanks,

1.13

1.130

kitchen and cost of re-erection of

4 Romneys

Submarine fresh water

pipeline

Security fence

Furniture & equipment

Contingency

0-75

0.750

3.00

3.000

2.00

2.000

1.00

1.000

HKD2.675 PDS0.223

HKD9.88 PDS0.823

HKD12.555

PDS 1.046

Amount committed to UK donation

Nil

In our Telno. 2923.

We requested PDS0.5m for the

Tai A Chau improvement works. Taking into account these additional requirements the cost estimate now stands at HKD9.88 million or PDS0.82 million.

Summary

Total required for completion of existing projects is sterling 5.548 million.

(a) High Island

sterling 3.0 million

sterling 1.125 million

(b)

Sek Kong

(c)

Ferries

sterling 0.6 million

(d) Tai A Chau Improvement Works -

sterling 0.823 million