FM HONG KONG

TO IMMEDIATE FCO

TELNO 1072

OF 03113OZ APRIL 89

INFO IMMEDIATE UKMIS GENEVA

7

YOUR TELNO 761 : VIETNAMESE BOAT PEOPLE: FINANCE

сн

THE ANSWERS TO YOUR QUESTIONS ON THE WHITEHEAD PROJECT ARE AS FOLLOWS:

(A) UNDER PRESENT PLANS STAGES 3 AND 4 OF THE WHITEHEAD PROJECT WILL INVOLVE THE ERECTION OF A TOTAL OF 40 PREFABRICATED DORMITORIES WITH ADDITIONAL BLOCKS FOR ESSENTIAL SERVICES (E.G. ADMINISTRATION, MEDICAL SERVICES, EDUCATION AND WORKSHIPS). THE COST OF INFRASTRUCTURE FOR THE CAMP (I.E. DRAINAGE, ROADS, WATER SUPPLIES AND POWER) WAS COVERED UNDER STAGES 1 AND 2 OF THE PROJECT. WORK COULD START ABOUT ONE MONTH FROM THE DATE FINANCE COMMITTEE APPROVES THE FUNDS. ONCE THE CONTRACT HAS BEEN SIGNED WE ESTIMATE THAT THE ACCOMMODATION WOULD BECOME AVAILABLE AT A RATE OF 2000 PER MONTH FROM THE FOURTH TO THE SEVENTH MONTHS. I.E. 2000 PLACES IN EACH OF THE FOURTH, FIFTH, SIXTH AND SEVENTH MONTHS. WE MIGHT BE ABLE TO REDUCE THIS SCHEDULE BY A MONTH OR SO BY CHANGING THE TENDERING PROCEDURES. WE ARE ALSO LOOKING AT

THE POSSIBLITY OF USING TWO-STOREY UNITS WOULD WOULD ENABLE US TO

INCREASE THE CAPACITY OF THE CAMP.

THE SCHEDULE OF EXPENDITURE WOULD BE AS FOLLOWS:

WORK

1ST MONTH

DELIVERY OF MATERIALS AND GENERAL

PREPARATORY WORK

FUND DISBURSEMENT CHK DOLLARS MILLION)

20

2ND AND

ASSEMBLY OF PRE-FABRICATED

3RD MONTHS

STRUCTURES AND CONSTRUCTION

40

4TH MONTH

STAGE 3A : 2,000 PLACES COMPLETED

25

5TH MONTH

STAGE 4A: 2,000 PLACES COMPLETED

20

1

PAGE

CONFIDENTIAL