CONFIDENTIAL

FM HONG KONG

TO IMMEDIATE FCO

TELNO 2125

OF 28110OZ JUNE 89

CONFIDENTIAL

HKB 2+3/11

75

054200

MDHIAN 1133

TOP COPY Q DIST ?

YOUR TELNO 1367 : VIETNAMESE BOAT PEOPLE : FINANCIAL ASSISTANCE FROM HMG

1. WE UNDERSTAND THE NEED TO PRESENT A SOUND CASE TO THE TREASURY

ON THESE PROJECTS. HOWEVER, IT IS IMPORTANT THAT WE MOVE QUICKLY IF

WE ARE TO AVOID DELAYS IN PREPARING NEW ACCOMMODATION. WE ALSO NEED

A DEGREE OF FLEXIBILITY IN DRAWING ON THESE FUNDS IF WE ARE TO BE

ABLE TO RESPOND TO RAPIDLY CHANGING CIRCUMSTANCES HERE.

2. WE HAVE THE FOLLOWING POINTS ON THE VARIOUS PROJECTS LISTED IN

PARA 3 OF TUR:

(A) WHITEHEAD 2(C) IT SHOULD BE UNDERSTOOD THAT THIS WAS NOT/NOT

A PART OF THE ORIGINAL PLAN FOR WHITEHEAD. WE HAVE DEVELOPED THIS

PROJECT IN RESPONSE TO THE VERY HIGH ARRIVAL RATE DURING MAY AND JUNE

AND THE PROSPECT OF FINANCIAL ASSISTANCE FROM HMG. WE ARE ALSO PLANNING TO USE DUTCH PREFABRICATED BUILDINGS FOR SEK KONG AND WE

HAD HOPED TO FUND BOTH PROJECTS FROM HMG'S ASSISTANCE. THE DUTCH

STRUCTURES ARE QUITE SIMPLY THE BEST VALUE FOR MONEY AND THE QUICKEST OPTION AVAILABLE TO US. WE HOPE YOU WILL BE ABLE TO CONVINCE TREASURY OFFICIALS THAT IT IS ESSENTIAL THAT WE PRESS ON WITH BOTH

PROJECTS IMMEDIATELY AND THAT WE NEED TO COVER THE COST FROM HMG FUNDS.

(B) SEK KONG. NEITHER HKG NOR HQBF HAVE A STOCK OF TENTS ON WHICH TO

DRAW FOR SEK KONG OR ANY OTHER PROJECT. THE TENTS USED AT SEK KONG

HAVE COME FROM THE SUPPLIES MADE AVAILABLE FROM UK (TWO CONSIGNMENTS) AND THOSE PURCHASED IN HONG KONG. WE WOULD LIKE TO CHARGE THE COST OF THE TENTS ALREADY PURCHASED LOCALLY (HK DOLLARS 4.75 MILLION) TO HMG'S CONTRIBUTION.

PROJECT ARE:

(I) DRAINAGE AND SEWERAGE

(II) SITE PREPARATION

(III) FENCEING

OTHER ELEMENTS OF THE SEK KONG

HKD 1 MILLION

0.75 MILLION

0.5 MILLION

(IV) WATER SUPPLY

(V) ELECTRICITY SUPPLY

2.5 MILLION

PAGE 1 CONFIDENTIAL

2.0 MILLION

Share This Page