-2-

The reactor and turbine buildings will be separate.

The seawater intake and pump house will be at the "non reactor" ends of the turbines with the discharge

leaving the plant area near the "reactor" end of unit 1

turbine.

3.2. State of the Works

and turbines.

The works executed comprised the site preparation,

excavation and low level foundations for the reactors

Most of the concrete poured was in the form of large slabs and blocks which constituted the sub bases for the major equipment.

The seawater pumphouse site was excavated and formwork for the pump intakes was under preparation (pumps are to be concrete volute type). The foundations in the

turbine area were generally still below turbine

basement level but the foundation block for the unit 1

condensate pumps (vertical canister type) was

substantially complete. It was difficult to determine

exactly where the turbine block columns would be since

the general level of the works was still well below the

point at which reinforcing starter bars or formwork

will be positioned. The bottoms of the cooling water

outlet culverts were complete and much of the

reinforcing for the vertical sides was in position. Formwork for the culverts was ready to be positioned.

The contractor had constructed a temporary, high level access roadway and platform adjacent to the site of the

turbine blocks. This was a significant item of

temporary works the full reason for which was not

clear. It was assumed that the contractor would use

this route to bring in all the block materials,

including concrete.