3
(a) fire hydrant hose reel;
(b) automatic wet sprinkler system;
(c) smoke and heat detectors;
(a) smoke extraction system;
(e) pressurisation of staircases;
(E)
fireman's lifts;
(g) emergency generators; and
(h) halon gas flooding system.
вс
An occupation permit for a building will not be granted
until the prescribed equipment has been installed.
Thereafter a registered contractor must inspect the
equipment each year and certify to the Director of Fire
Services that it is in good working order. If a fire
takes place in the upper floors before a building is
completed and before the anti-fire equipment has been
installed, to reach the floors above the 15th floor, the Department would have to lay hoses in order to
extinguish the fire (as they might well have to do on
the floors below the 15th floor if their access to the
building was blocked by the construction works).