Negotiation status of contracts other than three

main contracts

(a) Nuclear Island and Conventional Island Civil Works Contract

Through international competitive bidding and evaluation,

GNPJVC is holding the final round of negotiation with HCCM

(composed of French Campenon Bernard,

Campenon Bernard, Maeda Construction

Company Limited, Hua Xing Construction Corporation and the

Corporation).

2nd Bureau of China State Construction Engineering

The contract is expected to be signed in

May. In September 1986, GNPJVC signed a Pre-contract with

HCCM for the procurement of equipment and the local works,

which has laid the foundation for the main project to be

commenced in a very short time.

(b) Nuclear Island Erection Contract.

Following half year's preparations, bid specifications and

prequalification of potential tenderers have been

completed. The bid invitations were issued on 16th April,

1987 for world-wide competitive bidding. It is planned to

receive tenders in July and to award the contract in

November, 1987.

(c)

Conventional Island Erection Contract

The bid specifications are under preparation now. It is

planned to issue bid invitations in August 1987.

(d) In addition to the above-mentioned civil works and erection

contractor for QA consultancy contract has

contracts, the

been selected.

May.

The contract is scheduled for signature in

Enriched uranium supply contract is under negotiation

with French Cogema and Chinese Atomic Energy Corporation.

Of 24 lots of Balance of Plant, three contracts have been

signed following competitive bidding. Tenders are due to

be received in May for another two lots.