ROBABM (2)

BACKGROUND

1. The main contracts for the Daya Bay plant were signed in September 1986. A French contractor will supply the nuclear island: GEC will supply the turbines and generator. The plant is 25% Hong

Kong owned and some 70% of the power generated will go to Hong Kong.

2. On 15 September work on the first reactor raft was suspended

following the discovery that the spacing of reinforcement bars did

not comply with the original design. Although over 14,500

reinforcement bars were used in the first layer of the reactor raft,

only 260 of the required 576 inclined starter reinforcement bars

were included. These bars extend through each of the five layers of

concrete into the containment building wall.

3. Work resumed on 7 November after a report on the problem had

been prepared by the Joint Venture Company, and copy given to the Hong Kong Government. On the basis of the report and some supplementary information the Hong Kong Government were satisfied

that all reasonable steps had been taken to investigate the

circumstances of the problem, and that appropriate remedial measures

were being taken. The Hong Kong Government concluded that there

no compelling reasons why normal work at Daya Day should not

resume.

Mr Cohen asked an earlier question about the construction

problem on 30 October (text attached).

4.

Share This Page