28.11.86.

8.30

-

12.30

Reporter: PMO

contractor in preparing a case substantiating possibly for use

of substantiating any claims for delay, it was mentioned that it

was largely due to a lack of detailed design drawings

MR CHEUNG:

Yes, yes.

7

MR CHEONG:

8

9

supplied to the contractor at the beginning.

It was also mentioned in that particular report that the contractor is experienced

10

11

MR CHEUNG: Yes.

12

13

MR CHEONG:

and that they had just completed a project

14

with the

15

16

17

18

MR CHEONG:

19

20

21

from the construction stage

MR CHEUNG: Prince of Wales Building.

the headquarters for the British Armed

Forces, and it was also said that in that particular consultant's

report that detailed drawings were provided to the contractor as

Correct ? I mean I can refer you

22

back to the pages

23

24

MR CHEUNG:

Provided as it progressed.

25

26

MR CHEONG:

Well, I am stating a fact.

27

28

MR CHEUNG:

Yes.

29

30

MR CHEONG:

31

32

33

34

35

36

Now, if after bidding and winning the contract,

on Bills of Quantities, and don't forget even at the beginning of the bidding there were certain simple drawings or at least drawings provided to substantiate the Bill of Quantities, even if there were

no detailed designs provided at that stage, I can understand that it

would be possible to bid on the Bill of Quantities, but when the

contractor would have accepted the offer or the tender and when the

179