22.
(1) As soon as practicable after the
commencement of this Ordinance, the Road Company shall
submit to the Director for his approval a programme for the
carrying out of the construction works and the construction
works shall be carried out in accordance with such
programme as so approved.
(2) The Director may approve or disapprove the
programme submitted under subsection (1) or approve it in
part and disapprove it in part.
(3)
The Road Company may at any time apply to the
Director for a variation of the programme approved under
subsection (2) and any variation approved by the Director
under this subsection shall be deemed to form part of the
programme approved under subsection (2).
No works to
commence
without
authority..
23. Subject to sections 16 and 29, the undertaking of
any part or component of the construction works shall not
commence until